Senior Connects Project Plan


Project Start:
Project Finish:
Tue 2/3/04
Fri 5/7/04

Tasks

ID
Task Name
Duration Start Finish Resource Names % Complete
1
Research list of ILF
2 days Tue 2/3/04 Wed 2/4/04   0%
2
Survey Independent Living Facilities
3 days Tue 2/3/04 Thu 2/5/04   0%
3
Set meeting and meet with ILF Coordinator
4 days Fri 2/6/04 Wed 2/11/04   0%
4
Receive approaval from ILF Coordinator
3 days Thu 2/12/04 Mon 2/16/04   0%
5
Check and upgrade computer lab as required
7 days Tue 2/17/04 Wed 2/25/04   0%
6
Send Internet Survey and receive responses
7 days Tue 2/17/04 Wed 2/25/04   0%
7
Schedule classes
3 days Thu 2/26/04 Mon 3/1/04   0%
8
Begin classes
7 days Tue 3/2/04 Wed 3/10/04   0%
9
Classes
42 days Thu 3/11/04 Fri 5/7/04   0%

Resources

ID Name Group Max Units Peak Units

Assignments

Task ID Task Name Resource Name Work Start Finish % Work Complete

© 2003-2005 Senior Connects Corporation